| Condition Details / Information Notes |
| The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| The development hereby permitted shall be carried out and completed in accordance with the following approved plans and associated documents and the specifications and recommendations contained therein, except where otherwise stipulated by conditions attached to this permission
Block and Location Plan 100 P2
Proposed Site Plan 102 P7
Proposed Ground Floor Plan 201 P2
Proposed First Floor Plan 202 P2
Proposed Elevation Plan 401 P1
Reason: To ensure compliance with the approved scheme and policy SWDP 21 of the South Worcestershire Development Plan |
| The Development hereby approved shall not be brought into use until the customer parking and turning to include accessible bays, EV bays, demonstrator bays plus staff parking and display areas have been fully constructed, marked out and signed, as shown on drawing 2 5 0 0
1 J A D - 0 1 - X X - D R - A - 1 0 2 - P 5. These areas shall thereafter be retained and kept available for such uses at all times.
REASON: To ensure that satisfactory provision is made for the parking and turning of vehicles in conformity with the submitted details
|
| The Development hereby approved shall not be brought into use until the cycle parking shown on drawing 2 5 0 0 1 J A D - 0 1 - X X - D R - A - 1 0 2 - P 5 has been provided. Thereafter the provision shall be retained for the purpose of cycle parking only at all times.
REASON: To ensure that satisfactory provision is made for the parking of bicycles
|
| The Development hereby approved shall not commence until a Construction Traffic Management Plan has been submitted to and approved in writing by the Local Planning Authority. This shall include but not be limited to the following:-
• Measures to ensure that vehicles leaving the site do not deposit mud or other detritus on the public highway;
• Details of site operative parking, material storage areas and the location of site operatives facilities as required;
• Duration of works’
• Size, type and frequency of construction deliveries to include HGV routing;
• The hours that delivery vehicles will be permitted to arrive and depart, and arrangements for unloading and manoeuvring;
• Use of a banksman to oversee all vehicular manoeuvres, as required;
• Any temporary traffic management measures such as signage and / or cones in the highway will require a permit. Applications can be made via www.worcestershire.gov.uk
The measures set out in the approved Plan shall be carried out and complied with in full during the construction of the development hereby approved.
REASON: To ensure the provision of adequate on-site facilities and in the interests of highway safety.
|
| Before any above ground works are completed on the development hereby permitted a scheme of landscaping shall be submitted to and approved in writing by the Local Planning Authority. The landscaping scheme shall include:-
(i) a plan(s) showing the layout of proposed
planting
(ii) a schedule of proposed planting - indicating species, sizes at time of planting and numbers/densities of plants.
(iv) a written specification outlining cultivation and other operations associated with plant and grass establishment.
(v) a schedule of maintenance, including watering and the control of competitive weed growth, for a minimum period of five years from first planting.
All planting and seeding/turfing shall be carried out in accordance with the approved details in the first planting and seeding/turfing seasons following the completion or first occupation/use of the development, whichever is the sooner.
The planting shall be maintained in accordance with the approved schedule of maintenance. Any trees or plants which, within a period of five years from the completion of the planting, die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species.
Reason - To ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan. |
| Full details of any soil or soil forming materials proposed for importation to the site for use in garden areas, soft landscaping, filling, and level raising must be submitted to the Local Planning Authority and approved in writing prior to import and implementation of the scheme. The material must be assessed for contamination and suitability for use on site.
Full donor site details, proposals for contamination testing; including testing schedules, sampling frequencies and allowable contaminant concentrations (as determined by appropriate risk assessment), must be submitted to and approved in writing by the Local Planning Authority prior to import on to the site.
Following implementation of the approved scheme suitable validatory evidence (including but not exclusive to laboratory certificates, photographs, consignment notes, and relevant risk assessment) should be submitted to and approved in writing by the Local Planning Authority.
All works are to be carried out by competent persons and in accordance with the Environment Agencies 'Land Contamination Risk Management' guidance (LCRM).
Reason
To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property, and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
|
| In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported immediately to the Local Planning Authority. The applicant is advised to immediately seek the advice of an independent geo-environmental consultant experienced in contaminated land risk assessment, including intrusive investigations and remediation.
No further works should be undertaken in the areas of suspected contamination, other than that work required to be carried out as part of an approved remediation scheme, unless otherwise agreed by the Local Planning Authority, until requirements 1 to 4 below have been complied with:
1.
Detailed site investigation and risk assessment must be undertaken by competent persons in accordance with the Environment Agency's 'Land Contamination: Risk Management' guidance and a written report of the findings produced. The risk assessment must be designed
to assess the nature and extent of suspected contamination and approved by the Local Planning Authority prior to any further development taking place.
2.
Where identified as necessary, a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to identified receptors must be prepared and is subject to the approval of the Local Planning Authority in advance of
undertaking. The remediation scheme must ensure that the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990 in relation to the intended use of the land after remediation.
3.
The approved remediation scheme must be carried out in accordance with its terms prior to the re-commencement of any site works in the areas of suspected contamination, other than that work required to carry out remediation, unless otherwise agreed in writing by the Local
Planning Authority.
4.
Following completion of measures identified in the approved remediation scheme a verification report that demonstrates the effectiveness of the remediation carried out must be produced and is subject to the approval of the Local Planning Authority prior to the occupation of
any buildings on site.
REASON
To ensure that the risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property, and ecosystems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
|