| Condition Details / Information Notes |
| The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To comply with Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990.
|
| The development hereby permitted shall be carried out and completed in accordance with the following approved plans and associated documents and the specifications and recommendations contained therein, except where otherwise stipulated by conditions attached to this permission:
2346 3000A Basement as proposed plans
Reason: To define the permission.
|
| Prior to their installation, details and specifications for the cast iron decorative air bricks to be inserted into the stall risers shall be provided to, and approved in writing by the Local Planning Authority.
Reason: In the interests of safeguarding the historic environment.
|
| (A) No development shall take place until a Written Scheme of Investigation (WSI) for a programme of historic building recording has been submitted to and approved in writing by the Local Planning Authority. The scheme shall include:
1. A methodology for historic building recording that is commensurate with a Level 2 record, as set out in Historic England’s Understanding Historic Buildings: A Guide to Good Recording Practice (2016);
2. Confirmation that the work will be undertaken in accordance with Worcestershire Archaeological Standards and Guidance (2019);
3. A programme for analysis of the building record and any necessary post-recording assessment;
4. Provision for the dissemination of the record and analysis;
5. Provision for archive deposition of the final report and digital outputs; and
6. The nomination of a suitably qualified and experienced organisation or person to undertake the recording and associated reporting.
(B) The development shall not be occupied until the historic building recording and post-recording assessment has been completed in full accordance with the Written Scheme of Investigation approved under part A of this condition, and provision has been made for the analysis, dissemination, and archive deposition of the results.
Reason: In accordance with the requirements of paragraphs 207 and 218 of the National Planning Policy Framework 2012 (as amended) and SWDP 6 & 24 of the South Worcestershire Development Plan 2016 |
| (A) No below-ground works, including any reduction of ground levels, soil stripping, removal of existing surfaces, excavation for foundations, services, drainage, steps, or any other ground disturbance, shall take place until a programme of archaeological work, including a Written Scheme of Investigation (WSI), has been submitted to and approved in writing by the Local Planning Authority. The WSI shall include:
1. The methodology for archaeological site investigation and recording (watching brief);
2. The programme for post-investigation assessment;
3. Provision for analysis of the site investigation and recording;
4. Provision for publication and dissemination of the results;
5. Provision for archive deposition; and
6. The nomination of a competent person or organisation to undertake the work.
The development shall thereafter be carried out in accordance with the approved WSI.
(B) Where archaeological monitoring and recording of below-ground works is required, the development shall not be occupied until the site investigation and post-investigation assessment have been completed in accordance with the Written Scheme of Investigation approved under part (A) of this condition, and provision has been made for the analysis, dissemination, and archive deposition of the results.
Reason: In accordance with the requirements of paragraphs 207 and 218 of the National Planning Policy Framework 2012 (as amended) and SWDP 6 & 24 of the South Worcestershire Development Plan 2016 |
| The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material considerations, including planning policies and any representations that may have been received and subsequently determining to grant planning permission in accordance with the presumption in favour of sustainable development, as set out within the National Planning Policy Framework.
|
| Note: A fee is chargeable for the provision of archaeological curatorial services. The service includes advice and liaison throughout the archaeological works, including the provision of a brief (if requested), checking the Written Scheme of Investigation for compliance with local and national standards, monitoring fieldwork and ensuring any archaeological reports generated by the project are acceptable. The Archaeology and Planning Advisor will be happy to offer advice on all stages of the proceedings. Additional site visits will be chargeable at £60 per visit if required if it is considered that breaches of condition have taken place or when other situations arise that require a visit additional to the usual service.
As this scheme is considered to be a small-scale development of less than 1-ha the fee for curatorial services will be £248.00 (Inc VAT).
|