| Condition Details / Information Notes |
| The works hereby approved shall be carried out in complete accordance with the following plans, except where otherwise stipulated by conditions attached to this permission:
North Car Park Vehicle Tracking Plans (Drawing No: TRL-ONE-XX-XX-DR-C-0002. Rev: P01)
South Car Park Vehicle Tracking Plans (Drawing No: TRL-0NE-XX-XX-DR-C-0001. Rev: P01)
Site Plan (Drawing No: 2209 1300, Rev: B)
Residential Development Parking Justification Document produced by Firlands Transport Planning. Dated: 18th June 2026.
Proposed Elevations and Floor Plans (Drawing No: 2209 3100, Rev: G)
Reason: To ensure compliance with the approved scheme. |
| The development shall be carried out in full accordance with the refuse storage and details shown on the approved Site Plan (Drawing No: 2209 1300, Rev: B). The approved refuse storage facilities for each dwelling shall be provided in full prior to the first occupation of that dwelling and shall thereafter be retained and maintained for that purpose.
Reason: To ensure the satisfactory provision of this necessary residential facility in accordance with Policy SWDPR 28 of the South Worcestershire Development Plan Review 2026. |
| Provision shall be made before any dwelling is occupied for the provision of a shared system for satellite television using one satellite dish only on the new build which shall be submitted to and approved in writing by the local planning authority. The approved scheme, which shall include the siting, size and colour of the satellite dish.
Reason: To ensure that the development preserves the special architectural and historic interest of the listed building and the character and appearance of the conservation area, in accordance with Policy SWDPR 33 of the South Worcestershire Development Plan Review (2026) and Policies HE4 and HE6 of the National Planning Policy Framework (2026). |
| Full details of the following matters including any details shown on the submitted plans shall be submitted to and approved by the local planning authority in writing before any other additional groundworks are carried out
Schedule:
Rainwater goods
All external joinery
Meter boxes and external flue positions
The development shall not be undertaken other than in full accordance with such approved details.
Reason: To ensure that the development preserves the special architectural and historic interest of the listed building and the character and appearance of the conservation area, in accordance with Policy SWDPR 33 of the South Worcestershire Development Plan Review (2026) and Policies HE4 and HE6 of the National Planning Policy Framework (2026). |
| Notwithstanding any details shown on the submitted plans, prior to their first use on site suitably amended details of the following matters shall be submitted to and approved by the Local Planning Authority in writing
Schedule:
Windows to be recessed by minimum of 50mm
The development shall not be undertaken other than in full accordance with such approved details.
Reason: To maintain the character of the building and conservation area, in accordance with Policy SWDPR 33 of the South Worcestershire Development Plan Review (2026) and Policies HE4 and HE6 of the National Planning Policy Framework (2026). |
| Prior to their first use on site, samples of facing and roofing materials shall be submitted to and approved in writing by the local planning authority in writing. The development shall not be carried out otherwise than in accordance with such approved details.
Reason: To ensure a satisfactory standard of design and appearance for the development and the setting of the adjacent Grade II listed building in accordance with policies SWDPR 09 and SWDPR 33 of the South Worcestershire Development Plan Review 2026. |
| Details of any floodlighting/external lighting shall be submitted to and approved in writing by the local planning authority before the building(s) are occupied.
Development shall be carried out in accordance with the approved details.
Reason: Insufficient details were submitted for these matters to be fully and properly considered in respect of the approval hereby granted in accordance with policies SWDPR 09 and SWDPR 33 of the South Worcestershire Development Plan Review 2026. |
| During the construction works hereby approved no operations shall be carried out on the site other than between the hours of 08.00 to 18.00 Mondays to Fridays inclusive and 09.00 to 13.00 on Saturdays and no operations shall be carried out at all on Sundays or on statutory Bank Holidays.
Reason: To maintain the residential amenity of the surrounding residential development in accordance with policy SWDPR 28 of the South Worcestershire Development Plan Review 2026. |
| No deliveries shall be taken to or despatched from the site outside the hours of 09.30 to 14.30 on Mondays to Fridays inclusive on days when St Georges Catholic Primary School is open for children's attendance and 08.00 to 18.00 on all other weekdays and 09.00 to 13.00 on Saturdays. No deliveries shall be made on Sundays or statutory Bank Holidays.
Reason: To safeguard the amenity of, and avoid conflict with, users of the identified school(s) in close proximity to the site in accordance with policy SWDPR 28 of the South Worcestershire Development Plan Review 2026. |
| Unless otherwise agreed by the Local Planning Authority, other than that required to be carried out as part of an approved scheme of remediation, no additional groundworks shall take place until conditions 1 to 5 have been complied with:
1) A preliminary risk assessment (a Phase I desk study) submitted to the Local Authority in support of the application has identified unacceptable risk(s) exist on the site as represented in the Conceptual Site Model. A scheme for detailed site investigation must be submitted to and approved in writing by the Local Planning Authority prior to being undertaken to address those unacceptable risks identified. The scheme must be designed to assess the nature and extent of any contamination and must be led by the findings of the preliminary risk assessment. The investigation and risk assessment scheme must be compiled by competent persons and must be designed in accordance with the
Environment Agency’s “Land Contamination: Risk Management” guidance.
2) The detailed site investigation and risk assessment must be undertaken in accordance with the approved Scheme and a written report of the findings produced. This report must be approved by the Local Planning Authority prior to any development taking place.
3) Where the site investigation identified remediation is required, a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to identified receptors must be prepared and issubject to the approval of the Local Planning Authority in advance of undertaking. The remediation scheme must ensure that the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990 in
relation to the intended use of the land after remediation.
4) The approved remediation scheme must be carried out in accordance with its
terms prior to any other additional groundworks taking place, other than that required to carry out remediation, unless otherwise agreed in writing by the
Local Planning Authority.
5) Following the completion of the measures identified in the approved remediation
scheme a validation report that demonstrates the effectiveness of the
remediation carried out must be produced, and is subject to the approval of the
Local Planning Authority prior to the occupation of any buildings.
6) In the event that contamination is found at any time when carrying out the
approved development that was not previously identified it must be reported in
writing immediately to the Local Planning Authority. An investigation and risk
assessment must be undertaken and where necessary a remediation scheme
must be prepared, these will be subject to the approval of the Local Planning
Authority. Following the completion of any measures identified in the approved
remediation scheme a validation report must be prepared, which is subject to
the approval in writing of the Local Planning Authority prior to the occupation of
any buildings.
Reason: To ensure that risks from land contamination to the future users of the land
and neighbouring land are minimised, together with those to controlled waters,
property and ecological systems, and to ensure that the development can be carried
out safely without unacceptable risks to workers, neighbours and other offsite
receptors. |
| (A) No additional groundworks shall take place shall take place until a programme of archaeological work, including a Written Scheme of Investigation, has been submitted to and approved by the local planning authority in writing. The scheme shall include an ssessment of significance and research questions; and:
1) The programme and methodology of site investigation and recording.
2) The programme for post investigation assessment.
3) Provision to be made for analysis of the site investigation and recording.
4) Provision to be made for publication and dissemination of the analysis and records of the site investigation.
5) Provision to be made for archive deposition of the analysis and records of the site investigation.
6) Nomination of a competent person or persons/organisation to undertake the works set out within the Written Scheme of Investigation.
(B) No additional groundworks shall take place until the site investigation has been completed in accordance with Part A of the condition.
The development shall not be occupied until the post investigation assessment has been completed in accordance with the programme set out in the Written Scheme of Investigation approved under Part A and the provision made for analysis, publication and dissemination of results
and archive deposition has been secured.
Reason: In accordance with the requirements of the National Planning Policy Framework and SWDPR 09 & 33 of the South Worcestershire Development Plan Review 2026. |
| The Development hereby approved shall not be brought into use until the access, turning and parking facilities shown on the submitted Site Plan (Drawing No: 2209 1300, Rev: B) have been provided, with the spaces to be marked and allocated on the ground. These areas shall thereafter be retained and kept available for their respective approved uses at all times.
Reason: In the interests of highway safety in accordance with policy SWDPR 06 of the South Worcestershire Development Plan Review 2026. |
| The Development hereby approved shall not be occupied until the existing entry points on Thorneloe Walk as shown on the submitted Site Plan (Drawing No: 2209 1300, Rev: B) have been permanently closed up.
Reason: In the interests of highway safety in accordance with policy SWDPR 06 of the South Worcestershire Development Plan Review 2026. |
| A fee is chargeable for the provision of archaeological curatorial services. The service includes advice and liaison throughout the archaeological works, including the provision of a brief (if requested), checking the Written Scheme of Investigation for compliance with local and national standards, monitoring fieldwork and ensuring any archaeological reports generated by the project are acceptable. The Archaeology and Planning Advisor will be happy to offer advice on all stages of the proceedings. Additional site visits will be chargeable at £60 per visit if required if it is considered that breaches of condition have taken place or when other situations arise that require a visit additional to the usual service.
As this scheme is considered to be a small-scale development of less than 1-ha the fee for curatorial services will be 258.00 (Inc VAT). |